Frage 1
Frage
Most common cause of conflicts in a project is:
Antworten
-
Schedules
-
Technical Opinions
-
Personal Issues
-
Project Priorities
Frage 2
Frage
You are the Project Manager of the XYZ project. You want to find the planned expenses for next month. Which document do you need to refer to?
Antworten
-
Cost Management Plan
-
Cost Baseline
-
Cost Control Plan
-
Cost Variance report
Frage 3
Frage
You are working on the project of painting of your house. You identify a dependency that the painting of roof should begin only after two days of completion of painting of walls. This is an example of :
Frage 4
Frage
Control Procurements is a process in the Project Procurement Management Knowledge area.
Frage 5
Frage
Which of the following theory was suggested by Deming?
Antworten
-
Apply continuous small improvements to reduce costs and ensure consistency.
-
Marginal Analysis
-
Expectancy theory - people expect to be rewarded for their efforts.
-
Plan-do-check-act to improve quality.
Frage 6
Frage
You are required to estimate the time to paint a large wall. You know it takes two hours to paint one square foot of wall. The wall has an area of 30 square foot. So you estimate that it will take 60 hours to paint the wall. Which estimation model are you using?
Antworten
-
Bottom-up
-
Parametric modeling
-
Analogous
-
Expert judgment
Frage 7
Frage
In which process of Project Risk Management knowledge area are numeric values assigned to probabilities and impact of risks?
Antworten
-
Perform Qualitative Risk Analysis
-
Perform Quantitative Risk Analysis
-
Perform Numeric Risk Analysis
-
Plan Risk Response
Frage 8
Frage
Which of the following is an output of the Identify Risks process.
Antworten
-
Lessons Learned
-
Checklists
-
Risk Register
-
SWOT Analysis
Frage 9
Frage
The process of Conduct Procurements is part of the planning phase.
Frage 10
Frage
Which process identifies the project manager?