Question 1

Question
If a LEED project that is providing preferred parking for fuel efficient and low emitting vehicles has multiple parking lots, where should the preferred parking spaces be located?
Answer
  • preferred parking spaces only need to be provided in one lot
  • preferred parking spaces only need to be located in the lot designated for visitors
  • preferred parking spaces only need to be provided in the lot designated for staff
  • preferred parking spaces must be distributed among all lots

Question 2

Question
Which LEED recognized strategy will require chain of custody documentation as proof of credit compliance?
Answer
  • certified wood
  • rapidly renewable resources
  • recycled materials
  • regional materials
  • materials reuse

Question 3

Question
What is the greatest benefit of an integrative design process as it relates to a LEED project?
Answer
  • educating the project owner
  • reducing project soft costs
  • meeting building codes
  • shortening the project schedule
  • capitalizing on credit synergies

Question 4

Question
How many years can an agricultural product grow or be raised to be considered as rapidly renewable by LEED?
Answer
  • 10
  • 15
  • 20
  • 5

Question 5

Question
Which of the following strategies does not qualify as providing "preferred parking"?
Answer
  • providing a space that is as close to the building as possible
  • providing a designated covered spot
  • offering a significant discount on parking passes
  • providing a guaranteed space in a lottery system
  • providing a randomly assigned parking space

Question 6

Question
When are CFC based refrigerants allowed to be used in a LEED project?
Answer
  • if a CFC phase out is economically infeasible
  • if the refrigerant leakage rate is below 10% annually
  • in existing buildings
  • anytime

Question 7

Question
Which of the following is not a required design consideration for the recycling collection and storage area prerequisite?
Answer
  • protection from the elements
  • collection truck access
  • appropriate signage
  • convenient location

Question 8

Question
A project team is using cotton insulation that is grown and manufactured 100 miles from the project site. What credit(s) will the use of this material count toward?
Answer
  • rapidly renewable materials
  • recycled content
  • regional materials
  • recycled content and regional materials
  • rapidly renewable materials and regional materials

Question 9

Question
Which of the following project is considered to be a "soft cost"?
Answer
  • the architect's fees
  • carpet
  • money paid to the brick mason for labor
  • the project's structural steel
  • landscaping costs

Question 10

Question
What is required as documentation for each and every prerequisite and credit in the LEED for BUilding Designa nd Construction Rating System?
Answer
  • a project drawings
  • a required signatory
  • a letter template
  • photos
  • a project narrative

Question 11

Question
What is the minimum amount of pervious area a paving system must have to be considered "open grid"?
Answer
  • 40%
  • 50%
  • 30%
  • 60%
  • 20%

Question 12

Question
Solar reflectance is roughly synonymous with what term?
Answer
  • aquifer
  • glare
  • shielding
  • albedo
  • lumen

Question 13

Question
Which of the following is not considered to be a "basic service"?
Answer
  • Parking lot
  • church
  • bank
  • beauty salon
  • grocery store

Question 14

Question
One of the most cost effective ways to ensure optimal ongoing energy performance is to ______?
Answer
  • commission building systems
  • upgrade mechanical systems
  • maintain trees and landscaping features
  • install renewable energy systems

Question 15

Question
Which federal act has been adopted by many local jurisdictions and contains requirements for building accessibility?
Answer
  • EPAct
  • ANSI
  • ADA
  • Civil Rights Act
  • ASHRAE

Question 16

Question
A project generates 100 tons of waste throughout construction. 50 tons are collected off site and sent to a sorting facility with a facility wide diversion rate of 60%. 40 tons are separated on site and sent directly to recyclers. The final 10 tons are incinerated off site. What percentage of waste does LEED consider to have been recycled?
Answer
  • 40%
  • 50%
  • 80%
  • 70%

Question 17

Question
Which specific refrigerant has the highest global warming potential (GWP) of all the common refrigerants?
Answer
  • HCFC-123
  • CFC-502
  • CFC-11
  • HFC-404A
  • HFC-23

Question 18

Question
A project team is considering pursuing an innovation in design credit for a strategy that will require a large capital expense. The team decides that it will implement the strategy only if the strategy will be eligible for an innovation in design credit. What steps should the team take to determine whether its strategy will be eligible for the credit?
Answer
  • Research existing CIRs to see whether the strategy has been previously addressed
  • Draft a compelling narrative for the LEED submittal
  • Calculate the strategy's overall environmental impact and self evaluate whether it is significant
  • Check the LEED rating system

Question 19

Question
Which strategy supports improved indoor air quality?
Answer
  • avoid the use of products with high carbon dioxide concentrations
  • use filters with a low minimum efficiency reporting value (MERV) rating
  • use materials with recycled content
  • design systems to deliver ample outside air
  • eliminate refrigerants with ozone depletion potential
  • use advanced framing techniques

Question 20

Question
A new high rise residential building should use what LEED rating system for certification?
Answer
  • LEED for New Construction
  • LEED for Homes
  • LEED for Operations and Maintenance
  • LEED for Core and Shell
  • LEED for Interior Design and Construction

Question 21

Question
The regional priority credits for a project are based on what?
Answer
  • The project's city
  • the project's state
  • the project's county
  • the project's zip code

Question 22

Question
What costing model should be used to demonstrate the true cost of sustainability strategies?
Answer
  • simple payback
  • benefit analysis
  • return on investment
  • life cycle costing

Question 23

Question
What is the energy policy act used for in the LEED rating systems?
Answer
  • to set indoor air quality requirements
  • to establish baseline building plumbing fixture performance
  • to establish baseline building energy performance
  • to set product VOC limits

Question 24

Question
What is the first step in a successful waste management policy?
Answer
  • determine the embodied energy of the product
  • specify recyclable materials
  • recycle all possible construction materials
  • reduce the total quantity of waste
  • reuse existing materials

Question 25

Question
What is the first step a project team should consider when trying to save energy?
Answer
  • install sub metering equipment
  • use onsite renewable energy
  • reduce energy demand
  • adopt energy efficient measures

Question 26

Question
What happens if USBC finds out that a project does not meet the minimum program requirements (MPRs)?
Answer
  • the project's certification level is lowered by one level
  • the project must be resubmitted
  • certification can be revoked
  • a fine must be paid

Question 27

Question
The heat island effect may raise the temperature in an urban area by how many degrees above the temperature in nearby rural areas?
Answer
  • 10
  • 8
  • 2
  • 6
  • 4

Question 28

Question
What percentage of the solid waste stream each year is attributable to construction and demolition of waste?
Answer
  • 50%
  • 20%
  • 10%
  • 40%
  • 30%

Question 29

Question
What factor should a project team not consider when calculating life cycle costs?
Answer
  • maintenance costs
  • operating costs
  • initial costs
  • life span
  • none of the above

Question 30

Question
Which of the following transportation methods does not count as public transportation for LEED purposes?
Answer
  • subway system
  • campus shuttle or school bus system
  • bus
  • elevated rail system
  • taxi

Question 31

Question
Use of a dry urinal would decrease the fixture's water use form the Energy Policy Act baseline urinal water usage by how much?
Answer
  • 1.6 GPF
  • 2.5 GPF
  • 0.5 GPF
  • 1.0 GPF

Question 32

Question
LEED defined regional materials as originating within ____ miles of the project site?
Answer
  • 500
  • 700
  • 100
  • 250

Question 33

Question
Projects can identify which credits have regional priority by ____?
Answer
  • Checking the USGBC website
  • researching locally pertinent environmental issues
  • calculating the net environmental impact
  • submitting a CIR

Question 34

Question
Which type of refrigerant has an essentially zero ozone depletion potential (ODP) but still has high global warming potential (GWP)?
Answer
  • HCFCs
  • HFCs
  • CFCs
  • natural refrigerants

Question 35

Question
Which of the following is not a LEED accepted strategy for decreasing single rider, conventional automobile use?
Answer
  • providing preferred parking for fuel efficient and low emitting vehicles
  • charging fees for parking
  • locating the project near mass transit
  • providing only the amount of parking required by the zoning code
  • providing bicycle storage and showers

Question 36

Question
A building material that is made from recycled soda bottles contains _____?
Answer
  • pre-fabricated recycled content
  • post-industrial recycled content
  • pre-consumer content
  • post-consumer recycled content

Question 37

Question
Which LEED category has the most available LEED points?
Answer
  • water efficiency
  • indoor environmental air quality
  • location and transportation
  • energy and atmosphere
  • sustainable sites
  • materials and resources

Question 38

Question
Which strategy is not effective in reducing potable water use for irrigation?
Answer
  • mulching
  • rainwater harvesting
  • drip irrigation
  • spray irrigation
  • using native or adapted plants

Question 39

Question
What environmental problem is associated with CFC and HCFC use?
Answer
  • soil erosion
  • ozone depletion
  • the heat island effect
  • water pollution
  • air pollution

Question 40

Question
Which of the following strategies would not be appropriate for mitigating the heat island effect potential of the parking lot of a large office building?
Answer
  • use paving with a SRI of 35
  • place half of the parking underground
  • use open grid paving
  • use mature trees to shade 50% of the parking lot
  • plant seedling conifers to shade the parking

Question 41

Question
Which of the following is not a strategy for reducing stormwater runoff volume?
Answer
  • installing a vegetated roof
  • rainwater harvesting
  • minimizing the building footprint
  • increasing impervious paving
  • using bio retention

Question 42

Question
Which of the following types of vehicles does not qualify as an alternative fuel vehicle for the purposes of LEED?
Answer
  • Diesel powered
  • ethanol pwered
  • hydrogen powered
  • electric powered
  • hybrid (gas-electric)

Question 43

Question
How many of the 110 available points in most of the rating systems are considered bonus points?
Answer
  • 10
  • 20
  • 15
  • 5

Question 44

Question
Why should a project team aim to significantly exceed the established threshold of a LEED credit?
Answer
  • to save the world
  • to be an overachiever
  • as a precaution against a credit being audited
  • to earn exemplary performance

Question 45

Question
What strategy is being used for a project design that orients windows to allow the building to be warm in the winter, stay cool in the summer and capture daylight?
Answer
  • energy simulation modeling
  • high performance mechanical systems
  • passive design concepts
  • efficiencies of scale

Question 46

Question
Which type of system or equipment would not be a consumer of process water?
Answer
  • dishwasher
  • cooling tower
  • domestic hot water heater
  • clothes washer
  • food steamer

Question 47

Question
What is one potential disadvantage of using comingled recycling as a part of a construction waste management plan?
Answer
  • It is more difficult to document than site separated recycling
  • it may be more expensive than site separated recycling
  • it takes up more site area than site separated recycling
  • it may require a greater time investment from the project team

Question 48

Question
The CRI green label plus certification program certifies what type of building material?
Answer
  • furniture
  • adhesives
  • wood products
  • paint
  • carpet

Question 49

Question
Which of the following is not an acceptable form of renewable energy under the LEED rating systems?
Answer
  • low impact hydro-electricity
  • wind turbines
  • nuclear pwoer
  • geothermal
  • photovoltaic panels

Question 50

Question
Which type of refrigerant in general is the most efficient?
Answer
  • HFCs
  • CFCs
  • Natural refrigerants
  • HCFCs

Question 51

Question
Which of the following is not required of an Innovation and design strategy?
Answer
  • it must be a strategy not already covered in the LEED rating systems
  • it must be quantifiable
  • it must be cost effective
  • it must be repeatable by other projects
  • it must be comprehensive

Question 52

Question
Which of the following is not an approved strategy for minimizing the non-roof heat island effect?
Answer
  • shading hardscape with photovoltaiv panels
  • placing parking underground
  • using paving materials with an SRI of 29 or higher
  • using asphalt for parking areas
  • using open grid paving

Question 53

Question
Which rating system has a required recertification process?
Answer
  • Operations and Maintenance
  • Homes
  • Interior Design and Construction
  • Building Design and Construction
  • Neighborhood Development

Question 54

Question
If a project has 1 full time employee and 6 part time employees, what is the projects full time equivalent value (FTE)?
Answer
  • 6
  • 3
  • 5
  • 7
  • 4

Question 55

Question
What is the best use for potable water?
Answer
  • Drinking
  • cooling towers
  • toilet flushing
  • irrigation
  • swimming pools

Question 56

Question
What type of plant material is most appropriate for use on a green roof?
Answer
  • annuals
  • cultivated plant species
  • native plants
  • trees and shrubs

Question 57

Question
Which type of water is not allowed to be used for irrigation purposes?
Answer
  • Well water
  • gray water
  • captured rain water
  • potable water
  • black water

Question 58

Question
What is an appropriate use of the LEED logo?
Answer
  • for a link to the website
  • by a project pursuing LEED certificaiton
  • on product packaging
  • to indicate an organization's USGBC membership

Question 59

Question
What is not a possible source of graywater?
Answer
  • Washing machine
  • Toilets
  • Bathroom sink
  • showers
  • drinking fountain

Question 60

Question
What is true of the CIR process?
Answer
  • CIRs can be submitted by anyone with a USGBC account
  • all projects must use CIRs
  • CIRs cost $220 each
  • a successful CIR can aware LEED points

Question 61

Question
Demand controlled ventilation is typically adjusted in response to___?
Answer
  • VOC concentrations
  • a time schedule
  • occupant requests to the building operator
  • carbon dioxide concentraions

Question 62

Question
What sustainability concept can xeriscaping contribute to?
Answer
  • reducing the heat island effect
  • certified wood
  • indoor air quality
  • construction waste management
  • water efficient irrigation

Question 63

Question
Which material below is not considered a rapidly renewable resource?
Answer
  • bamboo
  • wood
  • cork
  • silk
  • straw

Question 64

Question
What is the best time to incorporate an integrative approach for a building project?
Answer
  • design development
  • construction documents
  • construction
  • schematic design
  • predesign

Question 65

Question
Which of the following regulations is likely to be contained in zoning regulations? (pick 3)
Answer
  • landscaping regulations
  • stormwater management regulations
  • regulations on energy usage
  • open space requirements
  • parking space requirements

Question 66

Question
Projects that achieve a projected water savings of at least ___ are eligible for an exemplary performance ID credit in addition to earning 4 points in WE indoor water use reduction.
Answer
  • 55%
  • 40%
  • 45%
  • 50%
  • 35%

Question 67

Question
What are some other possible LEED certifications a project may be able to receive if it has already received LEED core and shell certification? (pick 2)
Answer
  • LEED for schools
  • LEED for new construction
  • LEED for operation and maintenance
  • LEED for Homes
  • LEED for commercial interiors

Question 68

Question
A fuel efficient vehicle must meet which requirement to qualify as low emission and fuel efficient vehicles?
Answer
  • green label score of 30 or more
  • green label score of 45 or more
  • green e score of 25 or more
  • green seal score of 30 or more
  • green score of 45 or more

Question 69

Question
Which of the following products would be considered to contain post consumer recycled content that wuold contribute to the LEED credit for recycled content?
Answer
  • plumbing pipe made from recycled plastic components
  • steel beams made from used railroad ties
  • glass tiles made from glass broken during manufacturing
  • carpet made from recycled soda bottles
  • a countertop made from newspapers

Question 70

Question
During construction, if permanently installed air handlers are used, what is the minimum MERV rating for the filtration media needed to achieve IEQ credit: construction IAQ management plan?
Answer
  • MERV 8
  • MERV 6
  • MERV 7
  • MERV 10
  • MERV 5
  • MERV 9

Question 71

Question
What 3 standards can be used to achieve EA credit 1 Optimize energy performance? (pick 3)
Answer
  • Advanced buildings benchmark
  • CBECS
  • ASHRAE 90.1-2010
  • ASHRAE 62.1-2010
  • ASHRAE advanced energy design guide

Question 72

Question
What may prevent pedestrian access to a community resource? (pick 3)
Answer
  • a parking lot
  • a public park
  • a freeway interchange
  • distance
  • a wall

Question 73

Question
Which of the following materials may not contribute to construction waste management strategies? (pick 2)
Answer
  • concrete
  • product packaging
  • scrap wood
  • asbestos floor tiles
  • land clearing debris

Question 74

Question
What does the construction activity pollution prevention plan aim to prevent? (pick 3)
Answer
  • carbon emissions
  • solid waste generation
  • erosion
  • airborne dust pollution
  • sedimentation
  • construction worker accidents

Question 75

Question
Which standards are used to establish what vehicles qualify as low emitting and fuel efficient vehicles?
Answer
  • California air resources
  • green seal standard
  • american council for an energy efficient economy green book
  • green e prodcut
  • the greenguard certification program

Question 76

Question
The cost of LEED certification for new construction is based on which of the following?
Answer
  • USGBC membership and project type
  • project size
  • project size and USGBC membership
  • USGBC membership
  • project size and project type
  • project type

Question 77

Question
What is the cost of submitting a CIR?
Answer
  • 100
  • 0
  • 220
  • 500
  • 50

Question 78

Question
In addition to prohibiting smoking within the building, where is it also important to prohibit smoking to reduce occupant exposure to harmful airborne chemicals? (pick 2)
Answer
  • in covered parking spaces
  • in wooded areas
  • adjacent to building air intakes
  • near building entrances

Question 79

Question
Which of the following groups would be considered transient occupants? (pick 2)
Answer
  • college students
  • retail customers
  • office workers
  • factory workers
  • elementary school students

Question 80

Question
What happens after the construction submittal?
Answer
  • the full application is ruled upon by USGBC
  • construction points are awarded
  • the design submittal
  • design and construction points are awarded

Question 81

Question
What types of water on a residential condo project could not be used to qualify for WE credit 1 outdoor water use reduction? (pick 2)
Answer
  • captured rainwater
  • laundry water
  • recycled waste water
  • public water, non potable
  • kitchen sink water
  • black water

Question 82

Question
What are the two primary benefits of using regional materials? (pick 2)
Answer
  • minimizing the impacts of transportation
  • reducing costs
  • assuring quality craftsmanship
  • supporting the local economy

Question 83

Question
At minimum, which of the following basic materials should a recycling program designed to meet the storage and collection of recyclables prerequisite accommodate? (pick 3)
Answer
  • glass
  • plastics
  • cardboard
  • bulbs
  • ink cartridges

Question 84

Question
How can a project purchase green power? pick 2
Answer
  • By purchasing green e certified RECs
  • by buying energy directly from nearby wind farm
  • through a program by the local utility company
  • by purchasing and installing solar panels

Question 85

Question
Which of the following projects would definitely not meet minimum program requirements?
Answer
  • 5,000 SF fire station
  • casino on a riverboat
  • a brand new elementary school
  • renovation/addition to large office building
  • temporary sports practice facility

Question 86

Question
What two specific types of refrigerants does the Montreal Protocol phase out the use of? pick 2
Answer
  • CFCs
  • HFCs
  • natural
  • HCFCs

Question 87

Question
Two primary sources of potable water:
Answer
  • private/public well
  • ocean
  • captured rainwater
  • lake or stream
  • municipal water systems

Question 88

Question
What are some useful strategies to achieve WE credit: outdoor water use reduction? pick 3
Answer
  • use bioswales
  • use drip irrigation
  • remove turf grass
  • implement mulching
  • create a sediment basin

Question 89

Question
Which approaches can be taken to achieve WE credit outdoor water use reduction? pick 3
Answer
  • avoid mulch around flower beds
  • irrigate shrubs
  • micro misters
  • irrigate with captured rain water
  • native plants
  • use only mono species

Question 90

Question
What are ways to reduce storm water runoff volume?
Answer
  • create retention ponds
  • impervious paving
  • slowing water run off rates
  • use high albedo roof covering
  • use smaller building footprint
  • install bioswales

Question 91

Question
Local codes and regulations may affect which of the following strategies? pick 2
Answer
  • purchasing green power
  • minimizing parking capacity
  • managing indoor air quality
  • construction waste management
  • use of rainwater for toilet flushing

Question 92

Question
What is reduced when a project uses reclaimed water in its cooling towers?
Answer
  • process water use
  • irrigation water use
  • potable water use
  • nonpotable water use
  • indoor plumbing water use
Show full summary Hide full summary

Similar

Forms of Business Ownership Quiz
Noah Swanson
Unit 3 Business Studies
Lauren Thrower
Contract Law
sherhui94
AQA Business Unit 1
lauren_binney
Digital Marketing Strategy - The Essentials
Micheal Heffernan
What is Marketing?
Stephanie Natasha
Chapter 18 - Marketing mix(Product & Price)
irene floriane
Market Segementation
Noah Swanson
Business Studies - AQA - GCSE - Business Studies Key Terms
Josh Anderson
Business Marketing
s1500782
3. Enterprise, business growth and size
shlokashetty98