Crude Oil Pipeline System & Pipeline Configurations C

Description

Normal-level (N-level) Transmission and Storage Note on Crude Oil Pipeline System & Pipeline Configurations C, created by Yasmina Moussa on 27/10/2015.
Yasmina Moussa
Note by Yasmina Moussa, updated more than 1 year ago
Yasmina Moussa
Created by Yasmina Moussa about 9 years ago
11
0

Resource summary

Page 1

Crude Oil Pipeline System & Pipeline Configurations

Hydraulic Design Procedure system design comprises of three stages conceptual design system planning detailed engineering design conceptual design: product properties such as viscosity and gravity flow profile over the life of the project pipeline length and preliminary route with the points of injection and delivery Macro-economic data isothermal assumption is assumed when liquid is being transported near ambient temperature. this way hydraulics is minimal. temperature dependent classification of hydrocarbons: light hydrocarbon liquids --> non-isothermal flow intermediate hydrocarbon liquids heavy hydrocarbon liquids --> non-isothermal flow

Pipeline Configurations A pipeline network is composed of: injection points: inlet stations where the products are lifted into the line, storage facilities such as tanks and booster pumps are located there. Delivery points: terminal, product will be delivered to the final consumer or to the other pipelineIntermediate station: can provide a side stream injection or delivery pointpump stations: located along the line to move the liquid through the pipelineBlock Valve Stations: 1st line of consequence mitigation for pipelines. any segment can be isolated. they're located every 20-30 kmRegulating station: valve station where either pressure or flow is controlled. pressure regulates are located on the downhill side of a peak and flow regulates are found at delivery. Side Stream Delivery: dependent on: delivery flow requirements availability nomination status pipeline operational status design operations : Strip delivery through the branch line or at delivery point ful stream delivery through the branch line ful stream delivery through the main line design considerations: satisfying the delivery pressure requirements at both delivery locations while maintaining sufficiently high pressure at the take off point using a pipe with a smaller diameter downstream of the delivery point if side stream delivery volume is large installing an extra facility such as a pressure regulator or pump at the take off point on the branch line to stratify delivery pressure requirement selecting pumps to meet the maximum and minimum flow requirements: if inlet is shut down flow rate can be lower than side branch flow rate

Side Stream Injection side stream injection leads to adding flow rate to the mainline flow downstream of the injection pointfrictional pressure drop near the upstream segment is low due to low flow rate. block valve is installed upstream of the injection point on the mainline, its closed when a full stream injection takes place or a new batch is created. modes of side stream injection side stream injection through branch line or at original point of injection shutting down of the main line upstream injection point branch line shutting down if no volume is available to be injected into branch if a different product is injected into the mainline operational issues arise: two products are blended if a partial injection takes place, this changes the properties of the blended liquid from that of the original main line liquid. fluid at the mainline injection point will not progress down the mainline until the side branch injection is finished if the two products are not allowed to be blended; the injection should be a full stream injection. the main line flow is stopped upstream of the injection point design considerations: injection pressure on the branch line should be higher than the mainline pressure pipe with larger diameter can be used downstream of the injection point depending on injection volume pumps upstream of the injection point should be able to accommodate the reduced flow if partial side stream injection is present. if the side injection rate is high the upstream flow rate can be lower than the mainline flow. pumping units should accommodate viscosity difference in the downstream of the injection. side stream injection flow rate can be lower than minimum main line flow rate, pump stations should be able to meet the flow rate of the mainline. injection of the same product; no batch is created partial injection of a different product: a new blended batch with a different density and viscosity is created full stream injection of a different product: a new batch retains the product properties of the injection fluid

Pipeline in Series when different flow rates are transported due to intermediate take-off or injection or different pressures are required along certain pipe segments pipelines could be connected in a series. Different types of series arrangement: different pipe sizes different pipe wall thickness different pipe grade this provides different flow velocities but the same flow rate Pressure requirement for this section can be calculated by applying: flow equations for each section combining all the segment pressure drops total pressure requirements can be determined by calculating the pressure across all pipes Connection of different pipe sizes in series due to: change in flow change in elevation Connection of different pipe wall thickness due to: reduce pipe material and construction costs discharge pressure of an upstream pump is higher than deliver or suction pressure of a downstream pumppipe thicknesses are used to compensate for different pressure requirements, thinner for lower pressures (downstream) thicker for upstream. Connection of different Pipe Grade: may be used instead of using a pipe with different wall thickness to satisfy pressure requirement design. high grade= high pressure the use of different thicknesses or different grades is not a good option is more pump stations are added/ flow is reversed.the availability of a new pump in a thin or lower grade of a pipe obliges the pump to discharge at a lower pressure than initially needed.

Pipeline in Parallel pipelines are arranged in parallel to reduce the excessive pressure drop in certain sections of the pipelinetwo or more pipes are connected at the upstream and downstream points so that the flow splits among individual pipes and merges at the downstream pointthe split creates a common pressure across each pipe the sizes of pipes can be different along with the flow velocity

Show full summary Hide full summary

Similar

My Grades
Anastasia Korbut
Purpose of Homework Quiz
Rachel Marshall3149
1_Mind map about me.
taeler hamlin
Revision Time Table
jakevandromme
Hitler's rise to Chancellorship Jan '33
Simon Hinds
Data Structures & Algorithms
Reuben Caruana
B1 Revision
OmaimaE
Health and Safety Quiz
lynseyrogers23
History - Medicine through Time
Alice Love
Attachment - Psychology - Flash Cards
Megan Price
Astronomy Practice Quiz
cbruner