ASAP 8 Methodology Technical Solution Management Work Stream Quiz
Description
Diploma ASA380 - ASAP Implementation Methodology Quiz on ASAP 8 Methodology Technical Solution Management Work Stream Quiz , created by kim.t.dowling on 16/03/2016.
The SAP Going Live Check is split into two sections: Analysis and Verification. What are the recommendations regarding delivery of these sessions?
(More than one answer is correct. Please choose the correct answers.)
Answer
All sessions should be delivered before the project go-live.
All sessions should be delivered after the project go-live.
Going Live Analysis is conducted at minimum four weeks before the project go-live, during the realisation phase.
Going Live Verification is scheduled after the start of production, during the Go Live Support phase.
All sessions are delivered by certified consultants from SAP Active Global Support through a remote connection.
Question 2
Question
Which are the deliverables of the Technical Solution Management work stream in the Realisation phase?
Answer
Define General Settings and Master Data.
Quality Assurance Environment (QAS).
Technical Solution Design.
Technical Operations and Handover Plan.
SAP Going Live Check,
Question 3
Question
What is the purpose of the Technical Solution Management work stream in the project preparation phase?
(One answer)
Answer
To define General Settings and Master Data for the project.
To deliver QA and Production environments and finalize the development of the operations handbook.
To define and develop the Organisational and Production Support Readiness Check
To start preparation of essential technical and infrastructure deliverables that support the initial project planning of an SAP implementation project.
To prepare a strategy to hand off operations of the solution landscape to the post-production support organisation.
Question 4
Question
Which are the tasks of the deliverable 'Development Environment (DEV)' in the Blueprint phase?
(More than one answer is correct. Please choose the correct answers.)
Answer
Execute Technical Installation of SAP Products for DEV
Create master data in DEV environment - Master Data #1 - n
Conduct Design Review Service
Perform Manual Configuration in DEV
Import Configuration and Development Objects to QAS
Question 5
Question
Which transaction code in SAP Solution Manager is used to set up project documentation standards?
(One answer)